Project Limits:

The project was located on SR 54 in Sussex County. The limits extend from the intersection of SR 20 and SR 54 east to the Mallard Lakes development.

Project Need:

This area was identified as a high priority by Sussex County Council due to high development growth in the corridor over the last several years. Widening for a center left-turn lane provides operational improvements and improve the safety of the roadway, both for vehicular traffic as well as bicycles and pedestrians.

Project Overview:

The project widens SR 54 providing a center left-turn lane. The project also includes bike lanes and sidewalks.

Construction Start Date:

November 2010

Anticipated Completion Date:

Completed Summer 2012