Project Limits:

The project limits extended approximately 400 feet north and south of the intersection of US 113 and Millsboro Town Square/1st Street.

Project Need:

This project was recommended by the 2011 Hazard Elimination Program. The median opening on US 113 at Millsboro Towne Center and First Street had been the site of several accidents in the past few years.

Project Overview

This project installed an island in the median crossover to channelize movements in the median while still allowing left turns at this location for both northbound and southbound traffic.

Project Schedule:

Construction Start Date: July 13, 2016
Actual Substantial Completion Date – October 20, 2016 .

(Reviewed and Updated on 1/25/2017)