INFORMATION

Project Limits:

260' of roadway centered on the bridge.

Project Need:

The existing bridge consists of a 16' corrugated metal pipe arch with sacked riprap headwalls. The pipes have significant corrosion and has been selected by the Pontis Bridge Management System for work. Due to the deficiency rating and the structure's deterioration, a project has been initiated to replace this bridge.

Project Overview:

This project involves complete replacement of the existing structure. The existing pipe arch will be replaced with a 16' x 6' precast concrete rigid frame. Riprap will be placed upstream and downstream of the new structure for scour protection. Also included is 260' of new pavement, new guardrail and improvements to the roadside drainage.

Project Timeline:

Design Phase:

Design work to be completed no later than May 2018

Construction Phase:

Construction work to be completed December 2018