Bridge Construction
Construction Timeline
Design Bridge: 2008 - 2009
Mobilization: Winter 2008 - Summer 2009
Foundations/Concrete Piles: Winter 2008 - Summer 2009
Footings: Summer 2009 - Fall 2009
Substructure Abutments / Piers For Bridge Approaches: Summer 2009 - Fall 2009
Pylons: Summer 2009 - Summer 2010
Bridge Approach Spans: Winter 2009 - Spring 2010
Superstructure / Cable Stay: Spring 2010 - Winter 2010
Bridge Open to Traffic: Spring/Summer 2011

 

 

 

 

 

 

 

 

 

 

 

 

 
 