Bridge Construction
Construction Timeline
Design Bridge: 2008 - 2009
Mobilization: Winter 2008 - Summer 2009 Foundations/Concrete Piles: Winter 2008 - Summer 2009 Footings: Summer 2009 - Fall 2009 Substructure Abutments / Piers For Bridge Approaches: Summer 2009 - Fall 2009 Pylons: Summer 2009 - Summer 2010 Bridge Approach Spans: Winter 2009 - Spring 2010 Superstructure / Cable Stay: Spring 2010 - Winter 2010 Bridge Open to Traffic: Spring/Summer 2011 |
|