Project Limits:

Proposed roadway improvements extend east along Lorewood Grove Road from the Jamison Corner Road round-a-bout to the SR1 ramp at the DelDOT maintenance yard.

Project Need:

As a result of the planned development and the projected increase in vehicular, bicycle and pedestrian traffic in the Southern New Castle County area. DelDOT has started the process to make roadway improvement for multiple roadways in this area. Funding for the improvements will include Federal, State and private developer contributions.

Project Overview:

Proposed improvements include reconstructing Lorewood Grove Rd to include 12-foot travel lanes, 8-foot shoulders and a 10-foot shared use path.

Project Schedule:

This project will begin design in 2017
Anticipated Right-of-Way Acquisition – Begin Summer, 2019
Anticipated Start of Construction – Summer, 2021
Anticipated End of Construction – TBD

Scheduled meetings:

A public workshop will be schedule once the conceptual plans are completed. Public workshop notices will be mailed to residents in the neighboring communities and posted on the DelDOT website.


(Reviewed and Updated on 02/24/207)