INFORMATION

Project Limits:

Along Road A / SR7 from Stanton Christiana Road to Center Boulevard.

Project Need:

This project is proposed to address traffic congestion problems at along the stretch of roadway at and between the two intersections. The project will improve traffic flow and maintain acceptable levels of service. The project will also provide multi-modal improvements to the road.

Project Overview:

The project is currently proposed to improve Road A to provide three lanes of traffic in each direction across Route 1. A new bridge over Route 1 will be constructed to accommodate the additional lanes. A bicycle/pedestrian path is proposed from old Route 7 across the new bridge to Center Boulevard.

Anticipated Start Date:

Construction is anticipated to start in the Fall of 2018

Anticipated Completion Date:

Anticipated completion date Fall 2019

Scheduled Meetings

No new meetings are scheduled at this time.