Project Overview:

This project has two key components to the SR 24 corridor improvements:

SR 24 at Camp Arrowhead Road will:

  1. Widen the southbound Camp Arrowhead Road approaches to provide separate left-turn, pass through, and right-turn lanes.
  2. Extend the left-turn lane and right-turn lanes on all approaches to meet storage requirements.

SR 24 at Robinsonville Road/ Angola Road will:

  1. Widen the northbound and southbound Robinsonville Road/Angola Road approaches to provide separate left-turn, pass through, and right-turn lanes.
  2. Widen the westbound SR 24 approaches to provide a separate left-turn, pass through, and right-turn lanes.
  3. Extend the left-turn and right turn lanes on all approaches to meet storage requirements.

Project Need:

HSIP (Highway Safety Improvement Program) study prioritized improvements along the SR 24 corridor between SR 30 and the Love Creek Bridge. This project was identified in the study and as a high crash location that required improvements at the intersections.

Public Workshops:

April 16, 2018 Beacon Middle School - Public Notice | Displays

Project Schedule:

Final Design: Spring 2019

ROW Acquisition Start: Spring 2019

Construction Start: Late 2020