| AIRPORT RD (CR 319) | Vicinity: GEORGETOWN AIRPORT RD will close on 6/12/2021 for intersection improvements between US 9 and STERLIING AVE. Projected Completion Date: 8/27/2021 |
| HARMONY RD (CR355) | Vicinity: NEWARK HARMONY road will close on 7/19/2021 at the Amtrak Railroad crossing located between SR2 and OLD HARMONY RD. Projected Completion Date: 8/6/2021 |
| HARVEY STRAUGHN RD (CR7) | Vicinity: CLAYTON HARVEY STRAUGHN RD will close for bridge replacement over Black Stallion Ditch between MORRIS RD and OAK HILL SCHOOL RD beginning 7/6/2021. Projected Completion Date: 8/14/2021 |
| I 95 Northbound & Southbound | I-95 Northbound and Southbound will be restricted to a maximum width of 10 feet beginning 2/12/2021 located between the I-95/I-495 split and US202. For details or a hyperlink to images of the I-95 project please click on the NEWS link on the left tool bar and see the News Link item dated 2/4/2021. Project will operate in contraflow configuration until approximately 12/31/2022. Please see News link item dated 2/4/2021 to a hyperlink of updated images of the construction project. |
| NEWPORT GAP PIKE (CR21) | Vicinity: WILMINGTON NEWPORT GAP PIKE will close at the Railroad Crossing located between BOXWOOD RD and OLD CAPITOL TRAIL on 8/9/2021. Projected Completion Date: 8/20/2021 |
| SAWMILL RD (CR601) | Vicinity: GREENWOOD SAWMILL RD will close on 6/21/2021 for crossroad pipe replacement between TUCKERS RD and SR16. Projected Completion Date: 8/18/2021 |
| SILVER LAKE RD (CR 442) | Vicinity : MIDDLETOWN SILVER LAKE RD will close beginning 2/1/2021 for repairs to the dam located between NOXONTOWN RD and SANDBURG BLVD. Projected Completion Date: 8/20/2021 |
| SR 1 NB and SB | Vicinity: SMYRNA SR1 between NORTH SMYRNA (Exit 119) and SR 8 (Exit 98) will be restricted to a maximum height of 14' 4" for bridge painting beginning March 15, 2021. Projected Completion Date: 7/31/2021 |
| SR141 NB & SB (W BASIN RD) | Vicinity: NEW CASTLE SR141 Northbound and Southbound will be restricted to a maximum width of 10 feet between COMMONS BLVD and the US13 SOUTHBOUND RAMP beginning 8/2/2020. Projected Completion Date: 8/1/2021 |
| SR273 WB RAMP TO I95 SB (EXIT 3B) | Vicinity: NEWARK SR 273 Westbound ramp to I95 Southbound will close on 7/19/2021 for a ramp reconfiguration project. . Projected Completion Date: 8/23/2021 |
| SR273 WESTBOUND | Vicinity: NEWARK SR273 Westbound over I95 will be restricted to a maximum width of 12 feet beginning 7/19/2021 due to a ramp reconfiguration project. Projected Completion Date: 8/23/2021 |
| SR4 WB (CHRISTINA PARKWAY) | Vicinity: NEWARK SR4 WESTBOUND at the intersection with ELKTON RD will close beginning 7/8/2021 for concrete repair. Projected Completion Date: 7/30/2021 |
| SR9 (DELAWARE CITY PORT PENN RD) | Vicinity: PORT PENN SR9 will close to replace tide gates between REEDY POINT RD and THRONTOWN RD beginning 9/7/2021. Projected Completion Date: 1/8/2022 |
| US13 (SUSSEX HWY) | Vicinity: BRIDGEVILLE US13 Northbound and Southbound is now restricted to a maximum width of 18 feet between ADAMS RD and NEWTON RD. Projected Completion Date: 10/31/2021 |