Overview:

In an effort to get through the backlog of locations needing replacement, the Department advertised a contract in late 2016 to replace twenty-eight of these bridge-length CMP’s over a four year period.

The contract will be administered via the design-build contracting method. This means that DelDOT will select a team comprised of a contractor and engineering consultant through an evaluation process that considers both qualifications and price. The team that offers the best value through this process will be awarded the contract.

The twenty-eight locations are statewide and are listed below. The selected design-build team is required to perform public outreach during the design process for each location. This outreach will include updates to the web page for each location. In the meantime, click on the link below to find out background information for each site.

 

 

In the late 1970s and early 1980s, DelDOT replaced several hundred short span timber bridges with corrugated metal pipe (CMP) culverts, as shown in the above photo. These were inexpensive solutions to replace aging bridges at the time. However, they have reached the end of their service life and require replacement.


New Castle County

Bridge ID Road Name Stream Crossing Status
1420 461 Maryland Line Road Tributary to Sassafras River Easement acquisition in progress; Construction scheduled for Summer 2020
1454 465 Eagle’s Nest Road Saw Mill Branch Design complete; Construction scheduled for July 2020
1455 466 Deer Run Road Saw Mill Branch Easement acquisition in progress; Construction scheduled for Summer/Fall 2020

Kent County

Bridge ID Road Name Stream Crossing Status
2066A 066 White Oak Road Little River Complete July 2019
2113B 113 Cattail Branch Road Saulsbury Creek Design in progress; Construction Scheduled for 2021
2303A 303 High Stump Road Cattail Branch Design in progress; Construction Scheduled for 2021
2371B 371 Barratts Chapel Road Tributary to McGinnis Pond Design in progress; Construction Scheduled for 2021
2384C 384 Killens Pond Road Browns Branch Design in progress; Construction Scheduled for 2021
2442A 442 Abbotts Pond Rd Tantrough Branch Design in progress; Construction Scheduled for 2021

Sussex County

Bridge ID Road Name Stream Crossing Status
3132 565 Sunnyside Road Gum Branch Complete September 2019
3139 597 Tuckers Road West Branch Easement acquisition in progress; Construction scheduled for Fall 2020
3236 046 Elks Road Tributary to Hearn's Pond Easement acquisition in progress; Construction scheduled for Fall 2020
3317 024 SR24 Laurel Road Tributary to Trap Pond Easement acquisition in progress; Construction scheduled for Fall 2020
3323 447 Johnson Road Wileys Pond Design in progress; Construction Scheduled for 2021
3335 515 Bacons Road Meadow Branch Easement acquisition in progress; Construction scheduled for Spring/Summer 2020
3441 382 Armory Road Herring Branch Design in progress; Construction Scheduled for 2021
3564 413 Firemans Road Gum Branch Easement acquisition in progress; Construction scheduled for Summer/Fall 2020
3576 064 Whitesville Road North Fork Green Run Complete July 2018
3626 608 Ellendale Forest Road Maple Marsh & Beaver Dam Branch Complete April 2019
3627 606 Sammons Road Maple Marsh & Beaver Dam Branch Complete May 2019
3630 593 Maple Branch Road Maple Marsh & Beaver Dam Branch Easement acquisition in progress; Construction scheduled for Spring/Summer 2020
3913 016 SR16 Beach Highway West Branch Complete January 2020
3914 016 SR16 Beach Highway Stallion Head Branch Complete January 2020
3914A 016 SR16 Beach Highway Tributary to Stallion Head Branch Complete January 2020
3923 224 Fleatown Road Swiggets Pond Easement acquisition in progress; Construction scheduled for Spring/Summer 2020

Project Timeline:

  • Contract Advertisement – Contract was awarded to Zack Excavating in April 2017
  • Contract Execution and Notice to Proceed – Contract was executed in May 2017. NTP was issued on September 5, 2017
  • Design and Construction of twenty-five Locations – September 2017 through September 2021