Contractor Information
The Delaware Department of Transportation (DelDOT) anticipates advertising for bids for the construction of the US301, Maryland State Line to SR 1 project. The information on this website is provided only to assist potential contractors and suppliers in becoming familiar with the project. The various sections of information on this website are not Contract Documents and are provided for informational purposes only. Notice of the availability of the official Contract Documents will be posted on the State of Delaware Bid Solicitation Directory: http://bids.delaware.gov
Landscaping Contract, T201511301 will advertise in spring 2017. The second Landscaping Contract will advertise in spring 2018. Draft plans for T201511301 are available for viewing below.
IMPORTANT NOTICE - PREQUALIFICATION
As a prequalification to submit a bid on the US 301 project, all contractors and subcontractors must certify that their company, either independently or through agreement with other organizations, is providing craft training for journeyman and apprentice levels through a bona fide program approved by and registered with the State of Delaware and/or United States Department of Labor, to comply with 29 Del C. 6962(c)(11). A form is provided under the GENERAL INFORMATION tab that will be required to be submitted with any bid for the US 301 project along with program documentation. A Delaware Business License is not needed as part of the pre-qualification to bid. A Delaware Business License will be required as part of the contract award and execution process.
Anticipated Advertisement date is August 31, 2015. Questions to be directed to bids.delaware.gov after August 31.
- Roll Plans
- Construction Plans
- 001 to 016 Title, Index, Legend, Notes & Earthwork
- 017 to 058 Typical Sections
- 059 to 066 H & V Control
- 067 to 111 Construction Plans
- 112 to 159 Profiles
- 160 to 20 1Grades & Geometrics
- 202 to 218 Pavement Joint Layout Plans
- 219 to 223 Borrow Site Grading Plans
- 224 to 246 Construction Details
- 247 to 261 Structure Location Plan & Bridge 1-436-US301 Bridge Over Unnamed Tributary to Scott Run
- 262 to 313 Bridge 1-436A-Hyetts Corner Road Bridge Over US301
- 314 to 376 Bridge 1-458-Hyetts Corner Road Bridge Over Scott Run
- 377 to 437 Bridge1-460N-US301 Northbound Bridge Over Scott Run
- 438 to 496 Bridge 1-460S-US301 Southbound Bridge Over Scott Run
- 497 to 540 Bridge1-460A-Jamison Corner Road Bridge Over US301
- 541 to 580 Bridge 1-466 N & S-US301 North bound & Southbound Bridges Over SR896
- 581 to 594 Bridge 1-444-US301 Culvert At Wildlife Crossing
- 595 to 604 Maintenance of Streamflow Plans
- 605 to 621 Scott Run Stream Restoration Plans and Details
- 622 to 657 Stormwater Management
- 658 to 673 Environmental Compliance
- 674 to 709 General MOT, Notes, Permanent Warning Sign & Phasing MOT & E & S (1)
- 710 to 742 Phasing MOT & E & S & Detour Plans (2)
- 743 to 752 Landscaping
- 753 to 769 Lighting
- 770 to 775 Utility Relocation (1)
- 776 to 789 Utility Relocation (2)
- 790 to 830 Signing Striping & Conduit
- 831 to 832 Signal Plans
- 833 to 875 Ramp Toll Plaza Plans
- Specifications
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- General
- Roll Plans
- Construction Plans
- 001 to 011 Title, Index, Legend, Notes & Earthwork
- 012 to 031 Typical Sections
- 032 to 035 H & V Control
- 036 to 048 Construction Plans
- 049 to 061 Profiles
- 062 to 071 Grades & Geometrics
- 072 to 081 Pavement Joint Layout Plans
- 082 to 83 Borrow Site Grading Plans, Laydown Areas and Borrow Site Notes
- 084 to 103 Construction Details
- 104 to 107 Transition Slab Details
- 108 to 116 Barrier Wall Details
- 117 to 149 Structure Location Plan & Bridge 1-903S - SR-1 Southbound Bridge Over Scott Run
- 150 to 202 Bridge1-432 - US301 Northbound Bridge Over Scott Run
- 203 to 248 Bridge1-433 - US301 Northbound Bridge Over SR-1 (1)
- 249 to 292 Bridge 1-433 - US301 Northbound Bridge Over SR-1 (2)
- 293 to 299 Retaining Wall 1-1 Plans and Details
- 300 to 326 Retaining Wall 1-3 Plans and Details
- 327 to 359 Retaining Wall 1-3R Plans and Details
- 360 to 361 Maintenance of Stream Flow Plans
- 362 to 366 Stormwater Management
- 367 to 373 Environmental Compliance
- 374 to 401 General Traffic Control Notes & Phasing MOT & E & S (1)
- 402 to 427 Phasing MOT & E & S (2)
- 428 to 432 Detour Plans
- 433 to 449 Lighting
- 450 to 487 Signing Striping Conduit & Signal Plans
- 488 to 491 Right-Of-Way Plans
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Answers to your Questions
- Roll Plans
- Construction Plans
- 001 to 009 Title, Index, Legend, Notes, Earthwork
- 010 to 014 Typical Sections
- 015 to 018 H&V Control
- 019 to 033 Construction Plans
- 034 to 042 Profiles
- 043 to 057 Grades & Geometrics
- 058 to 065 Borrow Site Grading Plans
- 066 to 077 Construction Detail
- 078 to 084 Bridge 1-444A
- 085 to 124 Bridge 1-467
- 125 to 133 Bridge 1-468
- 134 to 152 Stream Restoration
- 153 to 166 Stormwater Management
- 167 to 183 Environmental Compliance
- 184 to 207 Phasing, MOT & E&S
- 208 to 219 Landscaping Plans
- 220 to 225 Wetland Mitigation
- 226 to 240 Signing, Striping & Conduit
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Answers to your Questions
- Roll Plans
- Construction Plans
- 001 to 010 Title, Index, Legend, Notes, Earthwork
- 011 to 020 Typical Sections
- 021 to 023 H&V Control
- 024 to 036 Construction Plans
- 037 to 049 Profiles
- 050 to 061 Grades & Geometrics
- 062 to 064 Pavement Joint Layout Plans
- 065 to 076 Construction Details
- 077 to 082 Structural Slab Details
- 083 to 095 Stormwater Management
- 96 to 99 Environmental Compliance
- 100 to 143 Phasing, MOT & E&S
- 144 to 146 Detour Plans
- 147 to 155 Lighting
- 156 to 159 Utility Relocation Plans
- 160 to 179 Signing, Striping, Conduit & Signal Plans
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Answers to your Questions
Anticipated Advertisement date is September 14, 2015. Questions to be directed to www.bids.delaware.gov after September 14.
- Roll Plans
- Construction Plans
- 0001 to 0020 Title, Index, Legend, Notes & Earthwork
- 0021 to 0055 Typical Sections
- 0056 to 0067 H & V Control
- 0068 to 0132 Construction Plans
- 0133 to 0187 Profiles
- 0188 to 2035 Grades & Geometrics
- 0236 to 0264 Construction Details
- 0265 to 0304 Bridge 1-468
- 0305 to 0355 Bridge 1-470
- 0356 to 0390 Bridge 1-472
- 0391 to 0440 Bridge 1-475
- 0441 to 0522 Bridge 1-477
- 0523 to 0560 Bridge 1-479
- 0561 to 0631 Bridge 1-480
- 0632 to 0666 Bridge 1-507
- 0667 to 0681 1-508A
- 0682 to 0685 1-508B
- 0686 to 0743 Stormwater Management Plans and Details
- 0744 to 0801 Stormwater Management Plans and Details
- 0802 to 0826 Borrow Site Wetland Mitigation Plans
- 0827 to 0858 Environmental Compliance Plans
- 0859 to 0861 Stream Relocation and Restoration
- 0862 to 0890 Phasing MOT & E & S
- 0891 to 0915 Phasing MOT & E & S(2)
- 0916 to 0945 Phasing MOT & E & S
- 0946 to 0968 Phasing MOT & E & S
- 0969 to 0999 Landscaping Plans
- 1000 to 1031 Lighting Plans
- 1032 to 1034 Utility Relocation Plan
- 1035 to 1112 Signing Striping and Conduit Plans
- 1113 to 1138 Maryland State Line to Levels Road
- 1139 to 1174 Maryland State Line to Levels Road
- 1175 to 1183 US301 & SR1 Interchange
- 1184 to 1241 Toll Plaza Plans
- 1242 to 1252 Spur Road Stockpile Plans
- 1253 to 1256 Middletown Electric Relocation Plans
- Specifications
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Roll Plans
- Construction Plans
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Hazardous Material Information
- Roll Plans
- Construction Plans
- 001 to 014 Title, Index, Legend, Notes & Earthwork
- 015 to 047 Typical Sections
- 048 to 057 H&V Control
- 058 to 103 Construction Plans
- 104 to 158 Profiles
- 159 to 160 Maryland Drainage Profiles
- 161 to 213 Grades and Geometrics
- 214 to 239 Construction Details
- 240 to 263 Pavement Joint Layout Details
- 264 to 291 Bridge 1-486
- 292 to 327 Bridge 1-482
- 328 to 338 Sign Structure Plans
- 338 to 388 Stormwater Management
- 389 to 438 Stormwater Management
- 439 to 445 Borrow Site Grading Plans
- 446 to 464 Environmental Compliance Plans
- 465 to 514 Phasing-MOT-Erosion
- 515 to 559 Phasing-MOT-Erosion
- 560 to 604 Phasing-MOT-Erosion
- 605 to 644 Phasing-MOT-Erosion
- 645 to 647 Detour Plans
- 648 to 665 Landscaping Plans
- 666 to 690 Lighting Plans
- 691 to 735 Utility Relocation Plans
- 736 to 792 Signing-Striping-Conduit Plans
- 793 to 799 Signal Plans
- 800 to 810 WIM and CVISN Plans
- 811 to 850 Tolling Plans
- Items and Quantities
- Geotechnical Boring Logs
- Cross Sections
- Answers to your Questions